The project required a significant amount of soil remediation due to perched groundwater and the poor soil characteristics of the existing clay and silt. Lime stabilizing was used to provide a stable base to place the 25,000-ton of imported sand required. This project also included a quarter mile of 28 feet deep 24” diameter RCP sanitary and a duplex stormwater pump station. This was Verdeterre’s first project for O’Brien Construction.